The above figure represents plan and section of an excavation layout. The volume of earthwork in excavation of foundation trench is
(a) 6.528 cu.m
(b) 8.064 cu.m
(c) 8.832 cu.m
(d) 9.600 cu.m
Answer : option B
Q.62. If d be the diameter of MS or tor steel bars in mm, the standard weight (in kg) per meter of the bar is
(a) 0.00618 d2
(b) 0.00618 d
(c) 0.00816 d2
(d) 0.00816 d
Answer : option A
Q.63. A level line is a
(a) line parallel to the mean spheroidal surface of the earth
(b) line passing through centre of cross hairs and centre of eye piece
(c) line passing through objective lens and the eye piece
(d) horizontal line
Answer : option A
Q.64. The following document contains detailed description of all items of work excluding their quantities, along with the current rates :
(a) Analysis of rates
(b) Tender document
(c) Abstract estimate
(d) Schedule of rates
Answer : option D
Q.65. Specific gravity has a unit:
(a) g/cc
(b) kg/m³
(c) N/m³
(d) No unit-dimensionless
Answer : option D
Q.66. To construct a massive dam the type of cement used is:
(a) blast furnace slag cement
(b) low heat cement
(c) rapid hardening cement
(d) ordinary Portland cement
Answer : option B
Q.67. A work costing Rs. 20,000 is termed as
(a) Petty work
(b) Minor work
(c) Major work
(d) Minor project
Answer : option A
Q.68. The density of cement is taken to be
(a) 1000 kg/m³
(b) 1250 kg/m³
(c) 1440 kg/m³
(d) 1800 kg/m³
Answer : option C
Q.69. The actual thickness of a butt weld when compared with the thickness of the plate is:
(a) less
(b) more or less
(c) more
(d) equal
Answer : option A
Q.70. The fillet weld whose axis is parallel to the direction of the applied load is known as:
(a) side fillet weld
(b) end fillet weld
(c) flat fillet weld
(d) diagonal fillet weld
Answer : option A
Q.64. The following document contains detailed description of all items of work excluding their quantities, along with the current rates :
(a) Analysis of rates
(b) Tender document
(c) Abstract estimate
(d) Schedule of rates
Answer : option D
Q.65. Specific gravity has a unit:
(a) g/cc
(b) kg/m³
(c) N/m³
(d) No unit-dimensionless
Answer : option D
Q.66. To construct a massive dam the type of cement used is:
(a) blast furnace slag cement
(b) low heat cement
(c) rapid hardening cement
(d) ordinary Portland cement
Answer : option B
Q.67. A work costing Rs. 20,000 is termed as
(a) Petty work
(b) Minor work
(c) Major work
(d) Minor project
Answer : option A
Q.68. The density of cement is taken to be
(a) 1000 kg/m³
(b) 1250 kg/m³
(c) 1440 kg/m³
(d) 1800 kg/m³
Answer : option C
Q.69. The actual thickness of a butt weld when compared with the thickness of the plate is:
(a) less
(b) more or less
(c) more
(d) equal
Answer : option A
Q.70. The fillet weld whose axis is parallel to the direction of the applied load is known as:
(a) side fillet weld
(b) end fillet weld
(c) flat fillet weld
(d) diagonal fillet weld
Answer : option A